Anti-termite treatment advisor background

Which termite treatment do you need?

New build or existing home, what is around the plot, the wood you use and any termites seen. Get the treatment, when it is done and how often to redo it.

New homes in Kerala get pre-construction soil treatment to IS 6313 Part 2, done in stages from the foundation pits to the plinth before the floor is laid. Existing homes get drill-and-fill treatment to Part 3, usually repeated every 3 to 5 years, or a bait system.

Advice and rates last updated 17 November 2026 · Checked by the Build 1 engineering team

How it is worked out

Following IS 6313.

The Indian Standard for anti-termite measures in buildings has three parts, one for each situation.

Part 1: design

  • Keep wood off the ground and away from damp.
  • Seal gaps where pipes and cables enter.

Part 2: before building

  • Soil under and around the foundation is treated in stages.
  • Imidacloprid, chlorpyrifos or bifenthrin at set strengths.

Part 3: existing homes

  • Holes along the wall-floor joint are filled with chemical and sealed.
  • The soil outside the walls is treated too.

Bait systems

  • Stations in the soil around the house, checked regularly.
  • No drilling and no chemical barrier near wells.
The numbers behind this tool

Every number is on this page, and dated.

Last updated 17 November 2026. Redo intervals used by the advisor; your pest-control partner may advise differently.

Intervals

Click a number in the editor to change it, then press Save.

Last updated

17 November 2026

Top up a pre-construction barrier after

10 years

Redo post-construction treatment, high risk

3 years

Redo post-construction treatment, normal risk

5 years

Renew a bait contract every

2 years

To change a number: open the site editor, click the number, type the new value and press Save. Material prices come from the shared rate table on the materials and brands page.

Questions

Questions about termites.

±Your pest-control agency inspects and confirms the treatment.
Ask your own question →
When should anti-termite treatment be done?

For a new home, during construction: the soil is treated in stages from the foundation pits to the plinth fill and the wall-floor joint, before the floor is laid. For an existing home, any time, ideally before the monsoon when termites are most active.

How long does it last?

A pre-construction barrier usually protects for 5 to 10 years with yearly inspection. Post-construction treatment usually needs to be repeated every 3 to 5 years, sooner where the risk is high.

Why are Kerala homes at high risk?

Damp soil, paddy land, coconut and rubber trees and heavy rain suit subterranean termites, and many homes use wooden doors, windows and ceilings.

Is it safe with a well nearby?

Keep the treated soil away from wells and use the right chemical and dose. Where a well is very close, a bait system avoids soil chemicals.

What should I ask the agency?

The chemical name and strength, the stages they will treat, photos of each stage, and a written warranty with yearly inspections.

Next step

Let’s protect your home.

Every good project starts with a clear conversation. Share your plot, approximate area, requirements and budget range, and we’ll suggest the right route and package.

Free site visit and plot check

Anywhere in Thrissur and Ernakulam districts.

Your price in writing in 7 days

Itemised, within 7 days of the site visit.

See a live site on a Saturday

Walk a Build 1 site with our engineer.

None added — use “Add to my brief” in Home Solutions.
We reply within one working day.
WhatsApp usCall +91 94973 07799

We reply within one working day.

Build 1 engineer on site
Talk to our team+91 94973 07799[email protected]Build 1, Irinjalakuda, Thrissur, Kerala
My brief (0) →