Material quantity calculator background

How much cement, steel and sand?

Cement bags, steel in tonnes, blocks, sand and aggregate for a whole house from its built-up area, or for one wall, slab, beam, column or footing. Check a contractor’s estimate in a minute.

A normal RCC home in Kerala with block walls uses about 0.4 bags of cement per sq ft of built-up area, roughly 400 bags for 1,000 sq ft, and about 3.5 kg of steel per sq ft for a single floor, 4 kg for G + 1 and 4.5 kg for G + 2. The structural design gives the exact quantities.

Rules and rates last updated 17 November 2026 · Checked by the Build 1 engineering team

1

What are you checking?

A whole house, or one part of it.

sq ft
300 sq ft8000 sq ft

About 186 sq m of built-up area.

How it is worked out

Thumb rules you can check.

Reviewed on 17 November 2026. Every factor is in the table further down.

Whole house

  • Cement 0.4 bags, sand 1.8 cft and aggregate 1.35 cft a sq ft.
  • Steel 3.5 to 4.5 kg a sq ft by floors.

Concrete

  • Dry volume = wet × 1.54.
  • M20 is 1 : 1.5 : 3, M25 is 1 : 1 : 2.

Walls

  • Blocks counted with 10 mm joints.
  • Mortar and plaster dry volume × 1.33.

Margins

  • 5% wastage on items, 3% on steel.
  • Cement in 50 kg bags at 1,440 kg a cubic metre.
The numbers behind this tool

Every number is on this page, and dated.

Last updated 17 November 2026. Standard thumb rules for RCC homes in Kerala; your structural engineer’s design replaces them.

General

Click a number in the editor to change it, then press Save.

Last updated

17 November 2026

Wastage margin, items

5 %

Wastage margin, steel

3 %

Whole house, per sq ft built-up

Thumb rules for a normal RCC framed home.

Cement

0.4 bags

Sand (M-sand + P-sand)

1.8 cft

Share of sand for plaster (P-sand)

40 %

Aggregate 20 mm

1.35 cft

Steel, single floor

3.5 kg

Steel, G + 1

4 kg

Steel, G + 2

4.5 kg

Solid blocks

1.0 pieces

Clay bricks

8 pieces

AAC blocks

0.6 pieces

Concrete

Nominal mixes: cement, sand, aggregate.

M15 mix

1, 2, 4

M20 mix

1, 1.5, 3

M25 mix

1, 1, 2

Dry volume factor

1.54

Cement density

1440 kg per cubic metre

Steel in slabs

80 kg per cubic metre

Steel in beams

130 kg per cubic metre

Steel in columns

160 kg per cubic metre

Steel in footings

80 kg per cubic metre

Walls and plaster

Block work and cement plaster.

Mortar joint

10 mm

Mortar dry volume factor

1.33

Plaster thickness

12 mm

Plaster mix, sand to 1 cement

4

To change a number: open the site editor, click the number, type the new value and press Save. Material prices come from the shared rate table on the materials and brands page.

Before you compare

Four things to ask for.

A quantity check only works if you can see what the estimate is based on.

1

Structural drawings

Footing, column, beam and slab sizes decide the steel and concrete.

2

Bar bending schedule

Lists every bar by diameter and length, so steel can be weighed on site.

3

Mix and grade

Ask whether slabs are M20 or M25, site-mixed or ready-mix.

4

Wall material

Blocks, bricks or AAC change the mortar, plaster and labour.

Questions

Questions about material quantities.

±A planning estimate. Your engineer’s design gives the exact quantities.
Ask your own question →
How many bags of cement for a 1,000 sq ft house?

About 400 bags, using the thumb rule of 0.4 bags a sq ft of built-up area for a normal RCC home with block walls and plaster. The structural design gives the exact number.

How much steel for a house per sq ft?

About 3.5 kg a sq ft for a single floor, 4 kg for G + 1 and 4.5 kg for G + 2. Long spans, cantilevers and poor soil need more.

How much sand and metal?

About 1.8 cft of sand and 1.35 cft of 20 mm aggregate for every sq ft of built-up area, split between M-sand for concrete and masonry and P-sand for plaster.

How do I check a contractor’s estimate?

Put in the same built-up area and floors. Cement and steel should be within about 10% of these figures for a normal home. If they are much higher, ask for the structural drawings and the bar bending schedule.

How is one wall or slab worked out?

From its size: concrete is converted to dry volume (× 1.54) and split by the mix ratio; walls count blocks with 10 mm joints and work out mortar and plaster from what is left. A 5% margin covers wastage.

Are the prices included?

Yes. The cost uses the dated dealer rates in the materials and brands directory, for materials only.

Next step

Let’s check your estimate.

Every good project starts with a clear conversation. Share your plot, approximate area, requirements and budget range, and we’ll suggest the right route and package.

Free site visit and plot check

Anywhere in Thrissur and Ernakulam districts.

Your price in writing in 7 days

Itemised, within 7 days of the site visit.

See a live site on a Saturday

Walk a Build 1 site with our engineer.

None added — use “Add to my brief” in Home Solutions.
We reply within one working day.
WhatsApp usCall +91 94973 07799

We reply within one working day.

Build 1 engineer on site
Talk to our team+91 94973 07799[email protected]Build 1, Irinjalakuda, Thrissur, Kerala
My brief (0) →